This feature provides two enhanced tracking views: “Effort tracking” and “Cost tracking”.

  • EAC and ETC information is calculated for both views.
  • Remaining Effort/Cost is synced to F&O as ETC forecast.

Configuration

This feature can be enabled from ‘Parameters > General > Projects360 parameters > Enable Enhanced Tracking View’.

  • This enhanced Tracking view will replace the MS standard one when activated.

Effort Tracking

This view gives project managers a clear picture of EAC/ETC information for all the tasks of the project based on pure effort.

  • “Effort tracking view” displays key information such as planned, actual and remaining effort as well as EAC and % Complete.
  • “Effort remaining” and “% Complete” can be manually updated by the user anytime.

  • View fields are listed below.
Fields Description
Project Task Name Displays name from project or Task
Project group Project group from project or task
Effort Effort from task. This field is rolled up by parent task
Effort Remaining Effort remaining from task. This field is rolled up by parent task. Editable at lowest level only
Actual Effort Number of hours posted by task. This field is rolled up by parent task
Effort EAC Effort EAC = Effort remaining + Actual effort
Effort Estimate at Complete from task. This field is rolled up by parent task
Estimated % Complete (Effort) % Complete = Actual Effort/ Effort EAC
This field is editable allowing the user to enter a new value if needed. Effort remaining will be calculated when a new value is entered
Effort Variance Effort Variance = Effort – Effort EAC
This field is rolled up by parent task

Cost Tracking

This view gives project managers a bigger understanding of the EAC/ETC project situation based on cost for both Labor and Expenses.

  • “Cost tracking view” displays key information like planed, actual and remaining cost for both labor and expense in only one view.
  • “Override cost rate” provides a way of manually overriding the cost for estimation purposes.

  • View fields are listed below.
Fields Description
Project Task Name Displays name from project or Task
Project group Project group from project or task
Effort Effort from task. This field is rolled up by parent task
Effort Remaining Effort remaining from task. This field is rolled up by parent task. Editable at lowest level only
Average Cost Rate It is the average price from all resources assigned to the Task
Override Cost Rate This field allows to override the average cost
If a value is entered/updated then “Cost Remaining”, “Cost EAC” and “Estimated % Complete” will be updated as well
Planned Labor Cost Planned Labor Cost = Effort * Average Cost Rate
This field is rolled up by parent task
Planned Expense Cost Sum of all “Total Cost Price” from Expense Estimates related to the specific Task
This field is rolled up by parent task
Planned Total Cost Planned Total Cost = Planned Labor Cost + Planned Expense Cost
This field is rolled up by parent task
Labor Cost Remaining If there is “Override Cost Rate”: Cost Rem = Effort Remaining * Override Cost Rate
If there is no “Override Cost Rate”: Cost Rem = Effort Remaining * Average Cost Rate
This field is rolled up by parent task
Expense Cost Remaining Expense Cost Remaining = Planned Expense Cost – Actual Expense Cost
This field is rolled up by parent task
Total Cost Remaining Total Cost Remaining = Expense Cost Remaining + Labor Cost Remaining
This field is rolled up by parent task
Actual Effort Number of hours posted by task. This field is rolled up by parent task
Actual Cost Rate Actual Cost Rate = Actual Labor Cost / Actual effort
Actual Labor Cost Actual cost rate from posted transactions
Actual Expense Cost Sum of the “Amount” from Actual transactions where “Transaction type” is “Expense” and “Transaction Class” is “Cost” related to the specific Task
Actual Total Cost Total Cost = Actual Labor Cost + Actual Expense Cost
This field is rolled up by parent task
Cost EAC Effort EAC = Total Cost Remaining + Actual cost
Estimated % Complete (Cost) % Complete = Actual Total Cost/Cost EAC
Cost Variance Cost Variance = Planned Total Cost – Cost EAC
This field is rolled up by parent task