Work item type Title VSTS ID Version
Enhancement The Fee Estimator’s performance has been significantly enhanced by introducing a formula parser, which efficiently processes complex calculation logic, leading to faster load times and improved responsiveness during estimate creation 99548 10.0.44.20250625
Enhancement The WBS planner performance has been significantly improved by introducing a formula parser that optimizes calculation logic. This results in faster load times, quicker updates, and smoother user experience when managing work breakdown structures 99544 10.0.44.20250625
Enhancement The Actuals table now includes Subproject ID and Transaction ID fields, allowing users to apply detailed filters and perform more accurate data comparisons across Project Operations and Finance & Operations 95332 10.0.44.20250625
Enhancement A new Unit Code Default Prices table has been added, enabling users to maintain default prices for each Unit Code and Company combination. These prices are automatically applied when creating Unit Estimates, ensuring consistency and reducing manual input 97126 10.0.44.20250625
Enhancement A new ‘Unit Estimates’ feature has been added to the Opportunity Line, enabling users to create a separate type of Fee Estimate. The values entered in Unit Estimates are automatically synced to the Unit Fees field within the Fee Estimator for seamless calculation 95654 10.0.44.20250625
Enhancement A new logging feature has been implemented to capture detailed errors and failures during WBS planner background processing. This enhancement provides better visibility into system operations and helps diagnose issues when users experience delays while the ‘WBS planner is being updated’ message is displayed 98049 10.0.44.20250625
Enhancement Timeout errors encountered while deleting labor items and moving task dates in large WBS structures have been addressed by synchronously enhancing the process. This optimization improves performance and ensures that these operations complete successfully without failures 103153 10.0.44.20250625
Issue Addressed an issue where users encountered errors during Effort Allocation publishing due to manual changes in WBS while the Effort Allocation was in draft. Now, the WBS planner is automatically locked during the draft stage to prevent conflicting updates and ensure a smooth publishing process 98910 10.0.44.20250625
Issue Addressed an issue where the Resource start date generated from the Team Members tab was not consistently reflected in the Team Members tab, Resource Requirement, and Schedule Board. The backend process has been enhanced to ensure consistent and accurate date alignment across all related tables 95708 10.0.44.20250625
Issue Addressed an issue where updating addresses on accounts in Project Operations resulted in duplicate address records in Finance & Operations. The synchronization process has been corrected to ensure that updates to primary and secondary addresses properly update existing records without duplication 98668 10.0.44.20250625
Issue Addressed an issue where P-project creation was failing without any error message due to invalid data in integration fields. The process has been enhanced to validate input data and provide users with clear error messages when issues occur, improving transparency and user guidance 102697 10.0.44.20250625
Issue Addressed an issue where task deletions in Project Operations after publishing were not syncing correctly to Finance & Operations. This fix ensures proper deletion synchronization for both Externally Scheduled and Projects for the Web projects 98995 10.0.44.20250625
Issue Addressed an issue where the ‘Copy from Fee Estimate’ process to WBS failed with a timeout error when processing a large set of labor items. The process has been enhanced to handle large data volumes efficiently and complete successfully 99166 10.0.44.20250625
Issue Addressed an issue where using ‘Copy from Fee Estimate’ on draft projects and then releasing the project to Finance & Operations resulted in unintended creation of additional subprojects and tasks. The process has been corrected to prevent duplication and ensure proper synchronization 97668 10.0.44.20250625
Issue Addressed an issue where, despite enabling ‘Activate Principal’ and ‘Project Accountant’ parameters, the corresponding fields were not visible in the Opportunity Line. This has been fixed, and the fields now appear as expected when the parameters are activated 99218 10.0.44.20250625
Issue Addressed an issue where Opportunities and P-projects failed to create when users attempted to create them on Fridays, due to Saturday’s working time being disabled in Finance & Operations. The issue has been resolved, and creation now functions correctly regardless of Saturday calendar settings 97976 10.0.44.20250625
Issue Addressed an issue where replacing a resource in Effort Allocation with a price multiplier applied did not correctly update the Updated Fee until publishing. The calculation now occurs immediately, enabling users to review accurate fees before publishing 99036 10.0.44.20250625
Issue Addressed an issue where copying Fee Estimates to WBS resulted in incorrect Estimated Expense Cost on the Project Summary tab, leading to discrepancies with WBS expense cost values. The calculation has been corrected, ensuring consistency across both areas 99029 10.0.44.20250625
Issue Addressed an issue where users were able to edit the Time Scale field by double-clicking, even when Effort Allocation was in draft stage. This behavior has been corrected to ensure the field remains non-editable during the draft stage 99061 10.0.44.20250625
Issue Addressed an issue where the project was getting released to FO with incorrect Actual Start Date. The issue occurred when the Actual Start Date field was present on the project or was being updated unexpectedly when subproject dates changed. The logic has been corrected to ensure the Actual Start Date aligns properly 99198 10.0.44.20250625